Roadway


Deprecated: preg_replace(): Passing null to parameter #3 ($subject) of type array|string is deprecated in /www/rqawdccm_789/public/wp-includes/kses.php on line 1805

I-70 Added Travel Lanes & Pavement Replacement

I-70 Added Travel Lanes & Pavement Replacement INDOT Greenfield District RQAW | DCCM is the Owner’s Representative and leading the environmental and front-end design services for the I-70 Design/Build. In this section, the RQAW | DCCM team is designing 1.1 miles west of Mt. Comfort Road to 1.3 miles east of SR 9 on I-70. The goal of this project is to increase capacity in addition to providing the following activities: Approximately 10 miles of added travel lanes in both directions Interchange modernization to meet current standards Pavement rehabilitation and reconstruction On-Ramp reconfiguration to include a multi-lane entrance ramp and an eastbound exit that will taper into a two-lane off-ramp Multiple bridge replacements and rehabilitations New signage, lighting, and ITS tower relocation and fiber extension Multiple small structure replacements Drainage construction and upgrades

I-70 Added Travel Lanes & Pavement Replacement Read More »

I-65 Added Travel Lanes Design-Build

I-65 Added Travel Lanes Design-Build INDOT Crawfordsville District I-65 Design-Build project spanned from SR 38 to SR 25, with a gross length of 8.08 miles. RQAW | DCCM provided survey, environmental, design, and mitigation services. The design included 7.8 miles of roadway reconstruction with added travel lanes in the median through three Lafayette-area interchanges. There were 14 structures completed with assorted treatments: preservation, deck overlays, deck replacements, and widening. The design included four noise barriers, ITS Weigh-In-Motion replacement, pavement markings, signing, and maintenance-of-traffic plans including median barrier walls. RQAW | DCCM served as INDOT’s representative throughout the life of the project. RQAW developed the scope of work and prepared the bid package for the design/build letting, which included 30% plans, special provisions, and cost estimate. After the letting, RQAW | DCCM assisted INDOT in the review and evaluation of the technical proposal packages submitted by the contractor/ designer teams, provided review and approval recommendations of the final plan submittals and shop drawings by the design/builder team, and partnered with the consultant inspector on the project to provide technical support on an as-needed basis.  

I-65 Added Travel Lanes Design-Build Read More »

Elkhorn Road Reconstruction

Elkhorn Road Reconstruction Knox County, Indiana RQAW | DCCM led this recently completed project, which involved the reconstruction of Elkhorn Road from the eastern side of the Elkhorn Road/US 41 intersection to the CSX Railroad crossing, approximately 730 feet northeast of the Elkhorn Road/Beckes Lane intersection. This road reconstruction project also involved realigning the Elkhorn Road/South Decker Road intersection, reconstructing roadside ditches, and replacing a large pipe with a 272-ft long 16-ft x 5-ft concrete box structure. RQAW | DCCM completed this project’s design and hydraulics, which opened in November of 2022.  RQAW | DCCM’s environmental staff also completed this project’s CE-2 environmental document and public involvement process due to permanent right-of-way exceeding 0.5 acres and stream impacts exceeding 300 linear feet. The environmental and design teams worked closely to assess the project’s environmental impacts accurately.

Elkhorn Road Reconstruction Read More »

Main Street & 4th Avenue Roundabout

Main Street & 4th Avenue Roundabout Carmel, Indiana This roundabout is located near a public library, school, and archway leading into the Carmel Arts & Design District; therefore, the geometry needed to be as small as possible to eliminate impacts to these areas while still allowing for school buses and emergency vehicles to make all necessary movements. Through our design, we were able to ensure that all turning movements and sight distance needs were met while minimizing the required right-of-way for construction. 

Main Street & 4th Avenue Roundabout Read More »

Redbird State Recreation Access Roadway

Redbird State Recreation Area Access Roadway INDOT Vincennes District This access roadway reconstruction project is within the Greene-Sullivan State Forest and the Redbird State Recreation Area. The project consisted of 7-ft to 11-ft wide travel lanes with 2-ft wide paved and 3-ft wide useable shoulders, resurfacing one county bridge deck, installing new guardrail, and replacing four existing small structures and several small drainage pipes. Four palustrine emergent and three palustrine forested wetlands were identified and delineated as well as 10 jurisdictional streams. RQAW | DCCM completed the State EA document and worked closely with the designers to remove several planned roadside ditches to avoid/minimize impacts to wetlands throughout the project.

Redbird State Recreation Access Roadway Read More »

US 36 Added Travel Lanes Phase 1

US 36 Added Travel Lanes Phase 1 Avon, Indiana | InDOT Crawsfordville District Paving the way for a growing community Challenge: The recent growth of Avon significantly influenced the initiation of the project, as it led to heightened safety concerns and increased traffic in this very commercialized area. Solution: US 36 from Shiloh Park Drive to Raceway Road was the first phase of a large-scale corridor improvement plan. RQAW | DCCM obtained traffic counts, developed a corridor model, and created an analysis to guide and refine the limits of this added travel lanes project. Through our findings, our team addressed the excessive traffic volumes by recommending an additional third travel lane in eastbound and westbound directions by proposing converting existing shoulders into travel lanes, turning the existing two-way left turn lane (TWLTL) into a curbed center median, and improving impacted intersections. Our approach resulted in no public controversy while minimizing construction costs, high crash rates, and the need for land acquisition. Cost $8.6M Completed 2023 Award  2023 ACEC Indiana Engineering Excellence Award Competition

US 36 Added Travel Lanes Phase 1 Read More »

SR 234 HMA Overlay

SR 234 HMA Overlay INDOT Crawfordsville District This partial 3R, minor structural overlay project located in Montgomery County was 11 miles in length and extended through the Town of Ladoga. The cross-section of the roadway remained unchanged, except at locations where two-ft shoulders were added within the existing right-of-way. The existing cross slope was corrected to two percent outside the town. Within Ladoga, the existing cross slope was perpetuated, and a Level 1 design exception was obtained. In addition, 19 curb ramps within Ladoga were replaced due to ADA deficiencies. New truncated domes were installed on four additional curb ramps. RQAW | DCCM coordinated extensively with the INDOT ADA Committee to minimize the impacts to the downtown area.

SR 234 HMA Overlay Read More »

SR 39 ADA Curb Ramps & Sidewalks

SR 39 ADA Curb Ramps & Sidewalks INDOT Crawfordsville District RQAW | DCCM was chosen to upgrade 32 curb ramps along SR 39 from Reagan Street to the north limit in the Town of Clayton. This project’s goal was to make all ramps ADA compliant; however, our team was able to utilize several innovative solutions throughout the design process. These solutions included inspecting existing ramps to determine if any grades and slopes were up to INDOT standards. Ramps that were found to be acceptable were maintained and any sites that were near satisfactory were retrofit with a detectable warning surface, rather than fully replaced. This process ultimately reduced the project cost by over 50%.

SR 39 ADA Curb Ramps & Sidewalks Read More »

Arlington Avenue & Shelbyville Road Roundabout

Arlington Avenue & Shelbyville Road Roundabout Indianapolis Department of Public Works This functionally obsolete intersection of Arlington Avenue and Shelbyville Road was originally a four-way, stop-controlled intersection with an approach that consisted of two 10-ft travel lanes in each direction. To accommodate the increasing amount of traffic in the area, RQAW | DCCM realigned Arlington Avenue to integrate a turning movement so that traffic, including semis, could navigate the roundabout properly. The final design was a small geometrical, single-lane roundabout with an inscribed circle diameter of 100 ft in a way that minimally impacted surrounding right-of-way and utilities. 

Arlington Avenue & Shelbyville Road Roundabout Read More »

Old Meridian Street & Carmel Drive Roundabout

Old Meridian Street & Carmel Drive Roundabout This project replaced a signal-controlled intersection and protected left-hand turning lanes with a 2-lane roundabout. The design avoided a $1.0M relocation on the northeast corner of the project. The intersection improvement upgraded the level of service, improved the overall safety of the intersection, and improved intersection control for the City of Carmel while increasing intersection capacity.

Old Meridian Street & Carmel Drive Roundabout Read More »

Scroll to Top